Factors Influencing The Quality of Construction Projects in Public Universities

Authors

  • Yohanes Aenet Jigjiga University, Ethiopia
  • Naruka Maniha Yesbud University, Ethiopia

DOI:

https://doi.org/10.47747/ijbme.v4i1.990

Keywords:

Project, Project Quality, Leadership Policy and Strategy, Partnership and Resource

Abstract

The study aims to determine factors affecting project quality in public universities in eastern Ethiopia. The researchers used primary data in a quantitative research approach to accomplish the objectives. The dependent variable, project quality, is regressed on five Explanatory variables: Leadership, Policy & Strategy, People, Partnership & Resources, and Process. Each of these characteristics was gathered from the consultant, client, and contractor. In order to determine the validity of the model. All multiple regression assumption tests were found to be valid. According to regression analysis, it was found that Leadership, Policy & Strategy, People, Partnership & Resources, and Process all have a substantial impact on project quality. The analysis from one-way ANOVA revealed that clients, contractors, and consultants have similar perceptions of the five quality attributes, leadership, people and policy and strategy, partnership and resources and process. Results from this research can be used by construction firms to improve their quality management systems, as they will indicate where the emphasis should be focused to ensure the ongoing improvement of project quality and sustainability.

 

Downloads

Download data is not yet available.

References

Abd-El-Hamied, E.M. and Mohamed, E.M. (2014) ‘Leadership importance in construction productivity improvement’, Journal of Management and Business Studies, 3(3), pp. 114–125.

Ahire, S.L., Golhar, D.Y. and Waller, M.A. (1996) ‘Development and validation of TQM implementation constructs’, Decision sciences, 27(1), pp. 23–56.

Anderson, E.W., Fornell, C. and Lehmann, D.R. (1994) ‘Customer satisfaction, market share, and profitability: Findings from Sweden’, Journal of marketing, 58(3), pp. 53–66.

Arditi, D. and Gunaydin, H.M. (1997) ‘Total quality management in the construction process’, International journal of project management, 15(4), pp. 235–243.

Assaf, S.A. and Al-Hejji, S. (2006) ‘Causes of delay in large construction projects’, International journal of project management, 24(4), pp. 349–357.

Atkinson, R. (1999) ‘Project management: cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria’, International journal of project management, 17(6), pp. 337–342.

Bassioni, H.A., Price, A.D.F. and Hassan, T.M. (2004) ‘Performance measurement in construction’, Journal of management in engineering, 20(2), pp. 42–50.

BBC News (2019) Challenges facing Ethiopia’s construction industry -. Available at: https://www.bbc.com/news/av/business-49503781.

Boljevic, A. (2007) ‘The importance of top quality management in contemporary management’, Serbian Journal of Management, 2(2), pp. 217–226.

Chan, A.P.C. and Tam, C.M. (2000) ‘Factors affecting the quality of building projects in Hong Kong’, International Journal of Quality & Reliability Management [Preprint].

Chinda, T. and Mohamed, S. (2008) ‘Structural equation model of construction safety culture’, Engineering, Construction and Architectural Management [Preprint].

Criado, F. and Calvo-Mora, A. (2009) ‘Excellence profiles in Spanish firms with quality management systems’, Total Quality Management, 20(6), pp. 655–679.

Dansoh, A. (2005) ‘Strategic planning practice of construction firms in Ghana’, Construction Management and Economics, 23(2), pp. 163–168.

EFQM Model (2003) ‘European foundation for quality management’, Brussels (Belgium) [Preprint].

EFQM Model (2013) ‘EFQM Representative Office: Brussels, Belgium, 2012’, Google Scholar [Preprint].

Elsaid, N.M., Okasha, A.E. and Abdelghaly, A.A. (2013) ‘Defining and Solving the Organizational Structure Problems to Improve the Performanceof Ministry of State for Environmental Affairs-Egypt’, International Journal of Scientific and Research Publications, 3(10), p. 273.

Fan, C.N. (1995) ‘Development of quality assurance in Hong Kong construction works’, Hong Kong Contractor [Preprint], (March/April).

Gan, Y. et al. (2017) ‘Critical factors affecting the quality of industrialized building system projects in China’, Sustainability, 9(2), p. 216.

Gharehbaghi, K. and McManus, K. (2003) ‘The construction manager as a leader’, Leadership and management in engineering, 3(1), pp. 56–58.

Gherbal, N. et al. (2012) ‘Critical success factors of implementing total quality management in Libyan organisations’, in International Conference on Industrial Engineering and Operations Management Istanbul, Turkey, pp. 80–89.

Gryna, F.M. and Juran, J.M. (2001) Quality planning and analysis: from product development through use. McGraw-Hill Science, Engineering & Mathematics.

Gujarati, D.N. and Porter, D.C. (1999) Essentials of econometrics. Irwin/McGraw-Hill Singapore.

Gul, S. et al. (2012) ‘Leadership styles, turnover intentions and the mediating role of organizational commitment’, in Information and Knowledge Management, pp. 44–51.

Hamid, H. (2015) ‘Continuous Improvement CSF framework for assessing ci maturity in ISO and non-ISO certified construction contracting organizations’. Universiti Tun Hussein Onn Malaysia.

Harris, F. et al. (2021) Modern construction management. John Wiley & Sons.

Inyang-Udoh, U.I. (2002) ‘Appraisal of Stock Control Systems on Building Sites’, Journal of the Nigerian Institute of Quantity Surveyors, 38(1), pp. 17–21.

Jha, K.N. (2011) Construction project management: Theory and practice. Pearson Education India.

Jha, K.N. and Iyer, K.C. (2006) ‘Critical factors affecting quality performance in construction projects’, Total Quality Management and Business Excellence, 17(9), pp. 1155–1170.

Joslin, R. and Müller, R. (2015) ‘Relationships between a project management methodology and project success in different project governance contexts’, International journal of project management, 33(6), pp. 1377–1392.

Jraisat, L., Jreisat, L. and Hattar, C. (2016) ‘Quality in construction management: an exploratory study’, International Journal of Quality & Reliability Management, 33(7), pp. 920–941.

Juran, J.M. (1992) Juran on quality by design: the new steps for planning quality into goods and services. Simon and Schuster.

Krejcie, R. V and Morgan, D.W. (1970) ‘Determining sample size for research activities’, Educational and psychological measurement, 30(3), pp. 607–610.

Kuhil, A.M. and Seifu, N. (2019) ‘causes of delay in public building construction projects: a case of Addis Ababa administration, Ethiopia’, Asian J. Manag. Sci, 8(2), pp. 4–9.

Lai, K.-H., Weerakoon, T.S. and Cheng, T.C.E. (2002) ‘The state of quality management implementation: a cross-sectional study of quality-oriented companies in Hong Kong’, Total Quality Management, 13(1), pp. 29–38.

Lam, S. and Tang, C. (2003) ‘Motivation of survey employees in construction projects’, Journal of geospatial engineering, 5(1), pp. 61–66.

Love, P.E.D. and Edwards, D.J. (2004) ‘Determinants of rework in building construction projects’, Engineering, Construction and Architectural Management [Preprint].

Mahalli, A.F. (2013) ‘Applying the EFQM model in performance measuring of organization’, Standard Research Journal of Business Management, 1(April), pp. 41–51.

Mahaney, R.C. and Lederer, A.L. (2006) ‘The effect of intrinsic and extrinsic rewards for developers on information systems project success’, Project Management Journal, 37(4), pp. 42–54.

Matlhape, M.G. and Lessing, N. (2002) ‘Employees in total quality management’, Acta Commercii, 2(1), pp. 21–34.

McAdam, R. and Kelly, M. (2002) ‘A business excellence approach to generic benchmarking in SMEs’, Benchmarking: An International Journal [Preprint].

Nepal, M.P., Park, M. and Son, B. (2006) ‘Effects of schedule pressure on construction performance’, Journal of Construction Engineering and Management, 132(2), pp. 182–188.

Oakland, J.S. (2014) Total quality management and operational excellence: text with cases. Routledge.

Olian, J.D. and Rynes, S.L. (1991) ‘Making total quality work: Aligning organizational processes, performance measures, and stakeholders’, Human Resource Management, 30(3), pp. 303–333.

Özutku, H. (2012) ‘The influence of intrinsic and extrinsic rewards on employee results: An empirical analysis in Turkish manufacturing industry’, Business and Economics Research Journal, 3(3), pp. 29–48.

Rezaian, A. (2011) ‘Time-cost-quality-risk of construction and development projects or investment’, Middle-East Journal of Scientific Research, 10(2), pp. 218–223.

Samson, D. and Terziovski, M. (1999) ‘The relationship between total quality management practices and operational performance’, Journal of operations management, 17(4), pp. 393–409.

Samuels, A.F. (1994) ‘Construction facilities audit: quality system-performance control’, Journal of Management in Engineering, 10(4), pp. 60–65.

Serpell, L. et al. (1999) ‘Anorexia nervosa: friend or foe?’, International Journal of Eating Disorders, 25(2), pp. 177–186.

Shanmugapriya, S and Subramanian, K. (2015) ‘Structural equation model to investigate the factors influencing quality performance in Indian construction projects’, Sadhana, 40(6), pp. 1975–1987.

Shanmugapriya, S. and Subramanian, K. (2015) ‘Structural equation model to investigate the factors influencing quality performance in Indian construction projects’, Sadhana - Academy Proceedings in Engineering Sciences, 40(6), pp. 1975–1987. Available at: https://doi.org/10.1007/s12046-015-0421-3.

Sureshchandar, G.S., Rajendran, C. and Kamalanabhan, T.J. (2001) ‘Customer perceptions of service quality: A critique’, Total quality management, 12(1), pp. 111–124.

Tan, R.R. and Lu, Y. (1995) ‘On the quality of construction engineering design projects: criteria and impacting factors’, International Journal of Quality & Reliability Management [Preprint].

Turk, A.M. (2006) ‘ISO 9000 in construction: An examination of its application in Turkey’, Building and environment, 41(4), pp. 501–511.

Uygur, A. and Sümerli, S. (2013) ‘EFQM excellence model’, International Review of Management and Business Research, 2(4), p. 980.

Vargo, S.L. and Lusch, R.F. (2004) ‘Evolving to a new dominant logic for marketing’, Journal of marketing, 68(1), pp. 1–17.

Wang, X. and Huang, J. (2006) ‘The relationships between key stakeholders’ project performance and project success: Perceptions of Chinese construction supervising engineers’, International journal of project management, 24(3), pp. 253–260.

Watts, C.A. and Hahn, C.K. (1993) ‘Supplier development programs: an empirical analysis’, International journal of purchasing and materials management, 29(1), pp. 10–17.

Yasamis, F., Arditi, D. and Mohammadi, J. (2002) ‘Assessing contractor quality performance’, Construction Management & Economics, 20(3), pp. 211–223.

Yusuf, A.A., Mofio, B.M. and Ahmed, A.B. (2007) ‘Proximate and mineral composition of Tamarindus indica Linn 1753 seeds’, Science world journal, 2(1).

Zenger, J.H. and Folkman, J. (2002) ‘The handbook for leaders: Extraordinary leaders’. McGraw-Hill, New York, NY.

Zikmund, B. (2013) ‘Carr, & Griffin (2010)’, Business research methods, 9.

Downloads

Published

2023-02-01

How to Cite

Aenet , Y., & Maniha, N. (2023). Factors Influencing The Quality of Construction Projects in Public Universities. International Journal of Business, Management and Economics, 4(1), 13 - 31. https://doi.org/10.47747/ijbme.v4i1.990